RFI log template
Requests for information: who asked, who answers, when it's due and whether it affects cost or schedule.
Use this templateFree for 14 days, no card needed. Already have an account? Choose it under New sheet.
| Subject | RFI # | Question | From | Sent | Response Due | |
|---|---|---|---|---|---|---|
| 1 | Beam size at grid C4 | 001 | Drawings show one beam size, the calculations another. Which governs? | Framing subcontractor | Jan 5 | Jan 12 |
| 2 | Window rough opening height | 002 | Confirm head height for the living room windows. | Site superintendent | Jan 6 | Jan 13 |
What you get
- 12 columns, set up with the right types
- 2 rows of examples (you can leave them out)
- Formulas that work things out for you
Columns
- SubjectText
- RFI #Text
- QuestionText
- FromText
- Assigned ToPerson
- SentDate
- Response DueDate
- StatusDropdown: Open, Answered, Closed
- OverdueFormula
- Cost ImpactCheckbox
- Schedule ImpactCheckbox
- ResponseText
More templates for Construction
Construction scheduleFrom permits to handover: phases, inspections as milestones, trades in sequence and the critical path.
Submittal logShop drawings, product data and samples: what's been sent for review and what's approved.
Change order logEvery change to scope, cost and time, who asked for it and whether it's approved.
Punch listItems to fix before handover, by location and trade. Comes with a form for site walks (attach photos to rows).
Daily site reportOne row per day: weather, crew, work done, delays and deliveries. Comes with a form for the site lead.
Start with the RFI log template
It’s ready in a few seconds. 14-day free trial, no card needed.
Use this template